Project Details | |
---|---|
CLIENT | Nottingham City Council |
BUDGET | £44,058.36 + VAT |
DATE | 2019 |
PROJECT TYPE | Premiership MUGA with acrylic coating and line markings |
The Brief:
The Client were looking to install a MUGA with drainage and acrylic coated surface. The surface was to be lined with 5-a-side football markings and basketball markings.
Equipment Installed:
• Premiership Fencing
• GO2000 Open Goals
• Cricket Wall
• Skills Wall
• Acrylic Surfacing in Green
• Basketball and Football line markings
• Drainage Holes
• Steel Seat
The Challenges:
The installation was completed within a public park so the site was protected with HERAS fencing to protect the public during build.
The installation was delayed slightly due to a delay in materials but the Client was kept up to date and realistic timescales were given.
Outcome:
The new MUGA has created a fantastic sports facility for all users to enjoy. With the addition of two multiactive panels the site is now suitable for football, basketball and cricket.
The site was constructed with green steel and green acrylic coating to blend in with the park surroundings. The site has been well used by local teams and groups in the area and is a great new addition for the community.